We have driven pile for many of the docks and piers owned by the Alabama State Port Authority, Alabama Shipyard, Atlantic Marine, Ingalls Shipbuilding and Bender Shipyard and Repair. Below are some of the many projects that we have been involved with from 1980 to the present time.
Alabama State Port Authority
Work Description: Drove 30" square concrete for ship loading dock
and piles for associated conveyor system.
Dauphin Island Bridge Fender System
Client: Brown & Root
Owner: Alabama Department of Transportation
Work Description: Drove 10" x 30" flat concrete sheet piles
drove timber piles, erected timber fenders, and associated
earth fill and rip rap fill.
U.S. Highway 98 Bridge over Big Creek Lake
Client: Hosea O. Weaver & Sons, Inc.
Owner: Alabama Department of Transportation
Work Description: Drove 12" H-piles for bridge support,
poured substructure concrete, erected prestressed girders.
East Bay Florida Oil Platform Protection
Client: H.G. Harders & Sons, Inc.
Owner: Getty Oil
Work Description: Drove steel sheet piling coffer dam with
removable gate to enclose oil drilling rig. Also drove several
pipe pile mooring dolphins.
Bridge over Fowl River on Bellingrath Road
Client: NewMc, Inc.
Owner: Mobile County Commission
Work Description: Drove 18" square concrete piles for bridge support.
Bridge over Escatawpa River on U.S. 98
Client:  NewMc, Inc.
Owner: Alabama Department of Transportation
Work Description: Drove 12" H-Piles for bridge support,
installed coffer dams for river piers.
Dauphin Island Fishing Pier
Client:  NewMc, Inc.
Owner: Dauphin Island Park and Beach Board
Work Description: Drove Class "B" timber piles and erected
timbers for 800' timber fishing pier.
I-65 Bridge widening in Mobile, AL
Client: Harbert International
Owner: Alabama Department of Transportation
Work Description: Drove concrete bridge support piles at
several bridge locations on I-65 in Mobile.
Berth "E" Warehouse Alabama State Docks
Client: Plant Maintenance Contractors
Owner: Alabama State Port Authority
Work Description: Drove 14" square and 16" square concrete
piles for warehouse at pier "D".
Berth "E" Alabama State Docks
Client: H.G Harders & Sons, Inc.
Owner: Alabama State Port Authority
Work Description: Drove 24" square concrete for ship loading
Roll on/Roll
off Dock and berthing dolphins.
Dock for Nucore-Yamatsu @ Blyville, Arkansas
Client:  H.G Harders & Sons, Inc.
Owner: Nucore-Yamatsu
Work Description: Drove pipe piles for dock, drove steel sheet pile cells
for breasting dolphins, drove steel sheet pile coffer inside steel mill.
Nine Bridges for Baldwin County, Alabama
Client: McInnis Corporation
Owner: Baldwin County Commission
Work Description: Drove 14" square concrete bridge support piles on
nine different bridges.
McDuffie Island Coal Handling Ship Unloading Dock No. 3
Client: R. J. Baggett, Inc.
Owner: Alabama State Port Authority
Work Description: Drove 20" square and 24" square concrete piles and
drove steel sheet piles for new ship unloading dock.
McDuffie Island Coal Handling
Client:  R. J. Baggett, Inc.
Owner: Alabama State Port Authority
Work Description: Drove 16" square and 20" square concrete piles for
conveyor system and barge loading dock.
U.S. Hwy. 98 and 31 over Tensaw River
Client:  McInnis Corporation
Owner: Alabama Department of Transportation
Work Description: Drove 36" square concrete piles, drove concrete
sheet piles, erected 72" bulb tees for bridge.
Liquid Bulk Terminal(Phenol)
Client: Ben M. Radcliff Contractor, Inc.
Owner: Alabama State Port Authority
Work Description: Drove 30" steel pipe piles, drove 18" square
concrete piles,
drove several steel sheet pile cells, erected steel
H-Pile fendering, installed timber fender system.
Bay 6 Ingalls Shipyard
Client:  Ben M. Radcliff Contractor, Inc.
Owner: Northrop-Grumman
Work Description: Drove approximately 2,000 16" square and
18" square concrete piles for dock expansion at Ingalls West
Bank Facility.
Pier D-2 Alabama State Docks
Client:  R.J. Baggett
Owner: Alabama State Port Authority
Work Description: Drove 20" square concrete piles, drove
steel sheet piles, fabricated and installed timber fender system.
Alabama Hwy. 231 Bridge over Chickasaw Creek
Client: Hosea O. Weaver & Sons, Inc.
Owner: Alabama Department of Transportation
Work Description: Installed and excavated coffer dams, drove
14" H-Piles, formed and poured all substructure concrete,
erected 72" bulb tees and Type III AASHTO girders, formed
and poured superstructure concrete.
Goat Rock Combined Cycle Generating Plant - Unit No.'s 1,2 & 3
Client: Southern Company Generation
Owner: Southern Company Generation
Work Description: Installed 3,300 14" diameter auger cast piles for three
combined cycle generating plants.
Southern Drain System Phase II
Client: City of Mobile
Owner: City of Mobile
Work Description: Installed steel sheet pile wall along drainage canal,
repaired and extended 5 timber railroad bridges.
Barry Steam Plant - Fender System & Mooring System
Client: Alabama Power Company
Owner: Alabama Power Company
Work Description: Fabricated and installed timber fender system, drove
20" diameter steel pipe piles for barge mooring system.
Choctaw Point Container Terminal
Client: American Bridge
Owner: Alabama State Port Authority
Work Description: Installed approximately 2000 LF of
PA50/AZ18. Combined wall, temporary sharing & pipe penetrations in 4
locations, drove 5874 LF of 18" & 11,554 LF of 24" square concrete
piles, all for new deck, relieving platform & crane rails.
Blue Creek
Coal Terminal
Client: R.J. Baggett
Owner: Walters Energy
Work Description: Installed 870 LF of PA48/AZ19.
Combined wall & 1460 LF of sheet pile wall, all for a new bulkhead.